…says S. Gurpreet Singh Sahni, CEO, Jeet Construction, in conversation with Pratima Agarwal. He shares that in the next 3 years, our aim to achieve a 60:40 mix, with 60% from Highways and 40% from non-highway segments to ensure stability. Excerpts……
What is Jeet Construction’s future business strategy?
Our strategy is focused on de-risking and sustainable growth. We are moving from a roads-only company to a diversified infrastructure player. We will continue to strengthen our core highway business while aggressively expanding into Irrigation, Water Supply, and Ropeway projects where government capex is high. Alongside this, we are investing in full mechanization and digital project management to deliver projects faster and with better margins.
Which are the main infrastructure segments contributing to Jeet Construction’s current revenue mix?
Presently, 75-80% of our turnover comes from Roads and Highways (NHAI/MoRTH/State PWD). The balance 20-25% comes from Irrigation and Building works. In the next 3 years, we aim to achieve a 60:40 mix, with 60% from Highways and 40% from non-highway segments to ensure stability.
Land acquisition has been a major hurdle in highway development. How can this be tackled?
In my view, three steps are needed:
1. Appointed Date should only be declared after 90%+ actual possession, not just notification.
2. A weekly joint review at district level between NHAI, Revenue Department and Contractor.
3. Complete digitization of land records and direct DBT of compensation to avoid litigation. NHAI’s recent policy of ensuring 80% Row before bidding is a very positive move.
Government entities award contracts on L1 basis. Critics claim L1 kills quality. Comment.
L1 is necessary for transparency in public procurement. The problem is not L1, but unworkable L1. The solution is to introduce Quality-cum-Cost Based Selection (QCBS) and give weightage to past performance, technical capability and timely completion record. Strict action against agencies that quote abnormally low and then fail to deliver will automatically protect quality.
Reasons for project cost escalations in road construction?
The main reasons are:
a) Delay in Land & Forest Clearance: Leads to idle machinery and overhead losses.
b) Price Volatility: Steel, bitumen and diesel prices can fluctuate 30-40% during a 2-year project cycle.
c) Change of Scope & Utility Shifting: Delays in shifting electric lines, water pipelines.
d) Geotechnical Variations: Especially in Himalayan states, actual soil conditions differ from DPR.
A more realistic and timely price escalation mechanism is the need of the hour.
Availability of trained manpower is an issue. How does Jeet Construction handle it?
The shortage of skilled operators, surveyors and quality engineers is about 30-40% in the industry. To tackle this, we have started our own in-house training center at our central yard to train local youth as heavy equipment operators and foremen. Secondly, we focus on retention better accommodation at site, timely salary, health insurance and incentives. We are also adopting more automated machinery to reduce dependency on scarce manual skill.